CASE STUDY: Maintaining Time to Power - Rescuing A Broken 190 MW EPMS Deployment

When poor quality control and software regression caused a legacy integrator to fail Phase 1 of a 190MW hyperscale data center build, the client faced severe timeline risks. We stepped in with less than three weeks notice. By deploying industry-standard Git version control and a synchronized on-site/off-site engineering strategy , we corrected existing code errors while simultaneously executing Phase 2, delivering the EPMS precisely on schedule.

Read the case study here.

Previous
Previous

CASE STUDY: Automating Upgrades & Commissioning For A 26,000-Device EPMS

Next
Next

PRESS RELEASE: AZZO Acquires Qubits Energy to Deliver Scalable Energy & Power Management for Data Centers and Other Mission-Critical Facilities